ACP quality check should verify that the delivered panel matches an approved construction, not merely that the surface looks acceptable. A complete review covers documents, batch identity, sizes, aluminum skins, coating, bonding, core evidence, fabrication behavior and packaging. This checklist helps buyers and project teams inspect building grade aluminum composite panels consistently before production. Test methods and acceptance limits must come from the applicable standard, contract and current maker datasheet.
Begin with the approved submittal and purchase order. Confirm product name, total thickness, skin gauge, alloy where specified, core, coating, color, sizes and quantity. Check that test reports and declarations identify the relevant product, manufacturing site, standard and revision. A certificate with a famous logo but an unclear scope does not verify the shipment. Link labels and packaging records to production batches so later checks can trace affected sheets. If a supplier proposes an alternative, pause approval until its construction and documents have been reviewed against the same needs.

Inspect sample panels under consistent lighting for dents, scratches, blisters, contamination, edge damage and protective-film problems. Measure length, width, diagonals and total thickness with calibrated tools at defined locations. Skin thickness may require a suitable measurement or verification method agreed with the supplier; do not infer it accurately from total thickness alone. Assess flatness on an appropriate reference surface and record the method because handling and support can change look. Any numerical tolerance should follow the contract or datasheet rather than an improvised onsite limit.
Compare delivered panels with the signed reference sample under agreed lighting and viewing angles. Metallic, spectra and textured finishes may need directional fitting and wider visual assessment than solid colors. Review coating identification, film-thickness evidence and relevant test records where specified. Check that protective film removes without unusual residue at the approved stage. A coating name alone does not prove weathering performance, so exterior projects should retain application and warranty conditions. For printable surfaces, approve ink adhesion using the actual printer and curing process described in our digital printing ACP guidance.
Aluminum skins must remain reliably bonded to the core through fabrication and use. Peel strength and other mechanical properties should be tested using recognized methods by competent personnel or laboratories; visual check cannot replace them. For routine production approval, make trial cuts, routed grooves and folded corners using the planned tools. Watch for delamination, coating cracks, excessive springback or damaged returns. Record settings and retain first-off samples. Our ACP fitting and fabrication guide explains why processing technique matters, but contract acceptance still requires the specified test evidence.
FR, B1 and A2 descriptions should be tied to identifiable core formulations and valid reports, not inferred from color or hardness. Review the standard, classification, laboratory, date and product scope. A reaction-to-fire report for the sheet may not demonstrate compliance of a complete facade or transport assembly. Added laminates, adhesives and insulation can alter the system assessment. Our fire-rated ACP classes article provides terminology, while the responsible project consultant should determine the required evidence. Isolate any shipment whose core description differs from the approved order.

| Inspection group | Typical record | Action on mismatch |
|---|---|---|
| Documents | PO, submittal, datasheet and report revisions | Hold technical approval |
| Appearance | Lighting, defects and photo references | Segregate affected sheets |
| Dimensions | Calibrated tools, locations and tolerances | Quarantine and remeasure |
| Coating and bonding | Approved samples and specified tests | Stop fabrication pending review |
| Packaging | Batch labels, protection and handling photos | Document damage before further handling |
Define sampling responsibility, sample size and acceptance rules before the shipment arrives. Photograph packaging and labels, select samples according to the agreed plan and keep them identifiable by batch. Record actual readings rather than writing only “pass.” Nonconforming panels should be physically separated and clearly marked to prevent accidental fabrication. Notify the supplier with objective photographs, measurements and affected quantities. Corrective action may involve replacement, sorting or additional testing, but it should be documented before the material returns to production.
Receiving approval can be undermined by poor storage or handling. Keep panels flat, dry and protected from impact, and use clean supports during cutting. Avoid dragging sheets across rough surfaces or leaving film exposed to sunlight beyond the recommended period. Installers should report new delamination, coating or edge defects instead of concealing them. FEITENG’s ACP technology resources and completed building panel project cases provide context for technical and look discussions, while each shipment still needs its own records.
Record instrument identification, calibration status and the exact measurement procedure. A thickness value is useful only when its location and method are known. For color and gloss, keep lighting, angle and reference samples consistent. Laboratory work should be assigned to competent facilities using the required standard.
A smooth face is an observation; peel resistance is a measured property. A rigid sheet is an observation; structural adequacy is an engineering conclusion. Keeping these categories separate prevents check reports from making claims beyond their evidence. State what was checked, what document was reviewed and what remains unverified.
Track each issue through containment, supplier response, correction and final approval. Do not close a case only because replacement panels arrived; inspect the new batch against the same criteria.
When a project requires third-party testing, agree sample selection and chain of custody before panels leave the factory. Randomly selected sample samples provide stronger evidence than a specially prepared example. Keep test sample labels connected to the same batch records used at receiving.
Use a shared check form for every batch. Include date, inspector, sample IDs and results. This creates comparable records across shipments and makes later audits faster.
Visual checks reveal many handling and coating defects, but they cannot verify skin gauge, bonding, core composition or fire classification. Combine look inspection with measurements, documents and specified tests.
Use the sampling plan in the contract or an agreed quality procedure. Quantity, batch size, risk and application affect sampling. Safety-critical or inconsistent batches may require expanded inspection or laboratory testing.
Possible factors include bonding production, incompatible processing, heat, moisture or mechanical stress. Investigation should review batch records and fabrication conditions rather than assigning cause from look alone.
No document should be accepted without checking product identity, scope, standard, revision and project applicability. The complete wall or transport assembly may require additional evidence beyond the panel report.
Follow the maker’s inspection and fitting instructions. Inspect sample surfaces at receiving while preserving protection where needed. Film condition and residue should be recorded if removal behavior is abnormal.
FEITENG has manufactured metal composite panels since 1994. This checklist is general guidance and does not define contractual acceptance limits. For current datasheets, samples and inspection coordination, contact the FEITENG ACP quality team with your specification and intended test needs.
Zhangjiagang Feiteng New Composite Materials Co., Ltd.
Address:No.77 Huada Road, Environmental & New Material Industry Park, Bonded Port Zone, Zhangjiagang City, Jiangsu, China
Phone:+86 18151586877
E-mail:info@feitengacp.com
COPYRIGHT © Feiteng All RIGHTS RESERVED.